Refurbishment works in this busy hotel which is also a spa included redecoration of guest bedrooms, bathroom re-fits, plastering and electrical upgrades. The safety of both our client’s staff and their guests were our utmost priority and as such we took extra steps to protect guest access routes to their rooms. During the project, we utilised 20 of our directly-employed operatives including two apprentices.
What we did
We replaced bathrooms and redecorated 96 rooms in busy Grade II listed hotel and spa.
Number of months
6
Contract Value
£
500
K
Year of construction
1871
Number of guest rooms
96
We recognised that unnecessary noise could disrupt guests but some noisy work was unavoidable. Collaborating with the hotel, we created a timed plan to minimise disruption, scheduling work for the afternoons when guests were more likely to be enjoying the spa facilities rather than being in their rooms.
innovations, challenges, solutions
We worked with the client to ensure disruption to guests was kept to a minimum.
023 8070 1111 | |